  • Changes to FATES beyond this time-frame should not be allowed to impact satellite phenology mode. The freeze will be complete once the clm6 feature freeze is completed (upon release).

    Overdue by 3 month(s)
    Due by June 15, 2025
  • Overdue by 28 day(s)
    Due by August 24, 2025
    4/4 issues closed
  • This milestone tracking effort lists the tasks required to have a version of FATES ready for the CLM6 release. These tasks include specific updates to the code (features, fixes, refactors, etc), calibrations and the resulting parameter sets delivered and testing performed. Code Updates: Calibrations: SP mode global 14 PFT set No-comp global 14 PFT set? Testing: iLAMB results Smoke tests on extended grids or extended length runs Timing tests

    Overdue by 1 month(s)
    Due by August 20, 2025
    6/6 issues closed