Description
Priority (1-3): 2
Impediment:
- not everything of the last sprint was merged into the right branch on time, so the release candidate did not contain all completed features
- not everything that could be released was release due to late submission
Notes:
- some team members finished their tasks last minute, that is why the release manager was struggeling (justifiably)
- one suggestion during the retro was to set a due time for pull request so the release manager has enough time to review the code and tag the release candidate
Solution:
- agree on a due time to open pull requests so the release manager does not come under tiem pressure