Priority (1-3): 2

Impediment:

  • not everything of the last sprint was merged into the right branch on time, so the release candidate did not contain all completed features
  • not everything that could be released was release due to late submission

Notes:

  • some team members finished their tasks last minute, that is why the release manager was struggeling (justifiably)
  • one suggestion during the retro was to set a due time for pull request so the release manager has enough time to review the code and tag the release candidate

Solution:

  • agree on a due time to open pull requests so the release manager does not come under tiem pressure